Key Compliance Attributes | Results as at June 30, 2020 |
---|---|
1.(a). % of staff with an internal audit or accounting designation (Certified Internal Auditor [CIA], Chartered Professional Accountant [CPA]). 1.(b). % of staff with an internal audit or accounting designation in progress (CIA, CPA). 1.(c). % of staff holding other designations (Certified Government Auditing Professional [CGAP], Certification in Risk Management Assurance [CRMA], etc.). | 1.(a) 39% of staff have an internal audit or accounting designation. 1.(b) 43% of staff with an internal audit or accounting designation in progress. 1.(c) 27% of staff holding other designations |
2.(a). Date of last comprehensive briefing to the Departmental Audit Committee on the internal processes, tools, and information considered necessary to evaluate conformance with the Institute of Internal Auditors (IIA) Code of Ethics and the Standards and the results of the Quality Assurance and Improvement Program (QAIP). 2.(b). Date of last external assessment. | 2.(a). The last briefing to Departmental Audit Committee (DAC) on the internal processes, tools, information necessary to evaluate conformance with the IIA Standards and the Quality Assurance and Improvement Program (QAIP) was on June 30, 2020. 2.(b). The last external assessment was completed in March 2016. Planned external assessment for 2020-21. |
3.Risk-Based Audit Plan (RBAP) and related information:
| Approved 2020-21 RBAP and related information (see table 1): See table 2 for the audits from 2019-20 (additions and adjustments to the internal audits listed in the Plan may have occurred in order to address emerging risks and priorities of the organization). |
4. Average overall usefulness rating from senior management (ADM-level or equivalent) of areas audited. | 4.Senior management of areas audited rated the overall usefulness of our work as "Good". |
Table 1- 2020-21 Risk Based Audit Plan – as at June 30, 2020
# | Internal Audit | Audit Status | Report Approved Date | Report Published Date | Original Planned MAP Completion Date | Implementation Status |
---|---|---|---|---|---|---|
1. | Carry Over from 2019-2020: Audit of Peace and Stabilization Operations Program | In progress | - | - | - | - |
2. | Carry Over from 2019-2020: Audit of Management Practices of Missions - Bamako, Mali | In progress | - | - | - | - |
3. | Carry Over from 2019-2020: Audit of Grants & Contributions Part I – Oversight & Monitoring | In progress | - | - | - | - |
4. | Carry Over from 2019-2020: Audit of Foreign Service Directive - Relocation | In progress | - | - | - | - |
5. | Advisory - COVID – 19 Emergency Repatriations to Canada | In progress | - | N/A | N/A | N/A |
6. | Advisory - Duty of Care – Governance & Spending | In progress | - | N/A | N/A | N/A |
7. | Advisory - COVID – 19 Remote Work Risk Assessment | Planned | - | N/A | N/A | N/A |
8. | Audit of Real Property – Strategic Investment & Portfolio Management | Planned | - | - | - | - |
9. | Advisory - Innovative Programming – Design Framework | Planned | - | N/A | N/A | N/A |
10. | Audit of Privacy Practices | Planned | - | - | - | - |
11. | Advisory - IT Risk Assessment Part I | Planned | - | N/A | N/A | N/A |
12. | Audit of Costing Methodology | Planned | - | - | - | - |
13. | Ongoing Data Analytics | Planned | - | N/A | N/A | N/A |
14. | Remote Mission Audit | Planned | - | - | - | - |
Table 2 – 2019-20 Internal Audit Status and Related Information – as of June 30, 2020
# | Internal Audit | Audit Status | Report Approved Date | Report Published Date | Original Planned MAP Completion Date | Implementation Status |
---|---|---|---|---|---|---|
1. | Audit of Grants and Contributions Monitoring and Oversight | Carry Over to 2020-2021 | - | - | - | - |
2. | Audit of Field Support Services | Completed | December 2019 | - | December 2020 | 50% |
3. | Audit of Information Management | Completed | June 2020 | - | June 2021 | 20% |
4 | Audit of Business Management Offices | Completed | December 2019 | July 2020 | September 2019 | 100% |
5. | Audit of Training Management Framework | Completed | December 2019 | July 2020 | September 2020 | 80% |
6. | Audit of Peace and Stabilization Operations Program | Carry Over to 2020-2021 | - | - | - | - |
7. | Audit of International Banking | Completed | December 2019 | - | September 2020 | 60% |
8. | Emergency Preparedness and Response (changed from audit to advisory due to COVID-19) | Completed | June 2020 | N/A | N/A | N/A |
9. | Advisory - Continuous Auditing Strategy – Acquisition Cards | Completed | June 2020 | N/A | N/A | N/A |
10. | Audit of Management Practices of Missions – Abidjan, Côte d’Ivoire | Completed | June 2020 | - | October 2020 | 70% |
11. | Audit of Management Practices of Missions – Beirut, Lebanon | Completed | December 2019 | July 2020 | March 2020 | 100% |
12. | Audit of Management Practices of Missions – Manila, Philippines | Completed | December 2019 | July 2020 | March 2020 | 80% |
13. | Audit of Management Practices of Missions – Bamako, Mali (replacement for Port-au-Prince, Haiti) | Carry Over to 2020-2021 | - | - | - | - |
14. | Advisory: Digital Data Strategy | Planned | - | - | - | - |
15. | Audit of Foreign Service Directive – Relocation | Carry Over to 2020-2021 | - | - | - | - |
16. | Audit of Foreign Service Directive – Education | Completed | December 2019 | July 2020 | June 2020 | 80% |
17. | Audit of Fleet Management | Completed | December 2019 | - | March 2021 | 40% |
18. | Advisory: Global Affairs Canada Renovation Project | Completed | December 2019 | N/A | N/A | N/A |